The 110/15 kV Pisz substation is ready

Elektromontaż Wschód has completed the modernization of new lagging compensation units at the 110 / 15kV substation commissioned by PGE The scope of work: preparation of project documentation, delivery of primary devices, modernization of the grounding unit stations and TPW1 and TPW2 for auxiliary needs, modernization of the 15 kV switch station, installation of a…

Construction of 110/15 / 1.3kV Dobczyn traction substation

Elektromontaż Wschód, as a general contractor, will build Traction Substation Dobczyn with power evacuation for railways under the government program MUZA III and MUZA IV. The scope of work includes: construction of internal roads, construction of the station’s external fence, construction of foundations: 110/15 / 1.3 / 1.3 kV transformer stations, transformer stations for own…

Another 110 / 15kV traction substation – Reptowo

Elektromontaż Wschód as a general contractor is involved in the construction of 110/15 kV substations in Reptowo for railways under the government program MUZA III and MUZA IV. The scope of work includes: construction of a 110kV power line input equipped with a three-pole circuit breaker, construction of a 110kV transformer bay, construction of a…

PT and RS Kietlanka 110/15/3 kV are started

Elektromontaż Wschód has completed the turnkey construction of the PT Kietlanka 110/15/3 kV traction substation, a 0.5 km WN double-circuit cable line with a pipe pole and a 110 kV RS Kietlanka network switch station. The scope of work included: construction of a railway building – PT traction substation, construction of internal roads and the…

GPZ 110/15kV Lewkowo from H1 to H4

Elektromontaż Wschód is modernizing the 110 / 15kV GPZ Lewkowo substation. The works are being carried out on a working station. The expansion of the 110kV switchgear from the H1 system to the H4 system along with the installation of new follow-up compensation devices includes the: construction of TR2, TPW2 stations, modernization of TPW1, construction…

GIS 110/6/0,5/0,4 kV for Polska Grupa Górnicza S.A.

We are implementing an investment agreement called Construction of the GST 110/6 / 0.5 / 0.4 kV Paniowy power station with accompanying infrastructure in the area of shaft VI for the needs of PGG S.A. The scope of works includes the comprehensive turnkey implementation: from designing and obtaining permits, to the construction and commissioning of…

We are building the SmartGrid network

On September 27, 2019, a contract was signed for the construction of a smart power grid in the city of Szczecin, Gryfino County and the city of Świnoujście. The investor is ENEA Operator Sp. z o.o. Under the contract, Elektromontaż Wschód will modernize and rebuild MV / LV stations and MV / MV network switching…

Modernization of the 110 / 20kV Sejny station

This is the third time that we carry out modernization works at this station. The first time we equipped the station with a telemechanics system – 2008. During the works in 2011, we installed an automatic voltage regulator 20 / 20kV imported by us from the United States. The current scope of work to be…

Extension of GPZ 110 / 15kV Żuromin

The scope of work includes the: extension of the 110 / 15kV GPZ Żuromin station with a new power line input related to the connection of Lubowidz-Zalesie FW, implementation of a construction design, execution design and turnkey construction of a new 110kV power line input in the active GPZ Żuromin station, installation of surge arresters…

GPZ Kolno with a two-system GIS 110kV switchgear

Elektromontaż Wschód, as the general contractor, has comprehensively modernized the 110/15 kV Kolno power substation. It is the first indoor, two-system 110kV GIS switchgear in the voivodship. The scope of work included the: modernization of the 110 / 15kV GPZ Kolno substation in GIS technology, turnkey modernization of the 110 / 15kV GPZ Kolno substation.…