GPZ 110/15 kV in Iłówiec near Poznań

At the request of Enea Operator, our companies will modernize another power station. Enspro will take care of the selection of optimal technical solutions, obtaining all the required opinions, approvals, decisions and permits, Elektromontaż Wschód will deal with delivery and assembly, and Elserwis with commissioning the station. As a result, the contract will be completed…

110 kV overhead line Ostrołęka

In Ostrołęka, the Elektromontaż Wschód company deals with the removal of a 110 kV overhead power line collision. The project involves, among other things, the dismantling of a part of the existing line and poles. In their place the new poles with a line will be installed along the new route. The works are expected…