Modernization of the Main Supply Point Stargard

Elmont Grupa – Infrastruktura Energetyczna

On behalf of Enea, Elektromontaż Wschód, as the general contractor, deals with the modernization of the Stargrad Main Supply Point station.

The scope of work includes:

  • the disassembly and construction of the new Morzyczyn-Kluczewo power line input,
  • the disassembly and construction of a new Morzyczyn I power line input,
  • checking and commissioning of the Morzyczyn-Kluczewo, Morzyczyn I bays,
  • the disassembly of the old stand and TR2 bay,
  • the installation of new TR2 bay,
  • voltage supply to the TR2 bay,
  • the construction works in the building,
  • the installation of lightning protection and grounding,
  • sanitary installation,
  • voltage supply to the newly built power line inputs: Morzyczyn-Kluczewo, PKP No. 2, Morzyczyn I and the transformer bay TR 2,
  • construction works in the control room building,
  • telemechanics,
  • external lighting,
  • Technical Protection System.
Elmont Grupa – Infrastruktura Energetyczna
Elmont Grupa – Infrastruktura Energetyczna

Share

See more

Photovoltaic farms

A 40MW photovoltaic farm in western Poland

Elmont, commissioned by a foreign investor, started the construction of a turnkey photovoltaic farm with a capacity of 40 MWp in western Poland. The farm

Energy infrastructure

Energy Storage 400 MWh

Enspro will carry ou the project, obtaining a permit for the construction of the HEP2 Battery Electricity Storage with a capacity of 200MW and a

Farma fotowoltaiczna Elmont
Photovoltaic farms

20 MW PV farm

Elmont is starting the construction of its next high-power photovoltaic farm. This time, at the request of a foreign investor in the Design and Build

See our projects